METHOD STATEMENT PACKAGE — HIGH-RISE BUILDING PROJECT

Total method statements: 114
Total editable Microsoft Word files: 228 (114 English + 114 Bahasa Malaysia)

IMPORTANT
Every template must be reviewed and adapted by a competent project team against the contract, approved drawings, project specification, actual site conditions, approved materials, manufacturer instructions, applicable Malaysian legal requirements and the Consultant's submission procedure before use.

CONTENTS
MS-CST-001 — Site Clearing and Disposal
MS-CST-002 — Surveying and Setting Out
MS-CST-003 — Earth Excavation
MS-CST-004 — Filling and Compaction
MS-CST-005 — Bored Piling
MS-CST-006 — Reinforcement Installation
MS-CST-007 — Concrete Formwork
MS-CST-008 — Reinforced Concrete Placement
MS-CST-009 — Precast Concrete Installation
MS-CST-010 — Structural Steel Fabrication and Erection
MS-ARC-001 — Brick and Block Walling
MS-ARC-002 — Wall Plastering
MS-ARC-003 — Floor Screeding
MS-ARC-004 — Floor and Wall Tiling
MS-ARC-005 — Wet Area Waterproofing
MS-ARC-006 — Painting Works
MS-ARC-007 — Suspended Ceiling
MS-ARC-008 — Door and Ironmongery Installation
MS-ARC-009 — Aluminium Window and Glazing
MS-ARC-010 — Roofing System Installation
MS-MEP-001 — Electrical Conduit and Trunking
MS-MEP-002 — Cable Pulling and Termination
MS-MEP-003 — Distribution Board Installation
MS-MEP-004 — Earthing and Lightning Protection
MS-MEP-005 — Domestic Water Pipework
MS-MEP-006 — Sanitary and Waste Pipework
MS-MEP-007 — Fire Sprinkler Pipework
MS-MEP-008 — Fire Alarm System
MS-MEP-009 — ACMV Ductwork Installation
MS-MEP-010 — ACMV Pipework and Insulation
MS-SAF-001 — Mobilisation, Hoarding and Site Facilities
MS-SAF-002 — Scaffold Erection and Dismantling
MS-SAF-003 — Crane Lifting Operations
MS-SAF-004 — Confined Space Work
MS-SAF-005 — Hot Work
MS-SAF-006 — Temporary Dewatering
MS-SAF-007 — Controlled Demolition
MS-PBG-001 — Driven Piling
MS-PBG-002 — Micropile Installation
MS-PBG-003 — Diaphragm Wall Construction
MS-PBG-004 — Basement Excavation and Strutting
MS-PBG-005 — Soil Nailing and Slope Stabilisation
MS-IBS-001 — Precast Wall Panel Installation
MS-IBS-002 — Hollow Core Slab Installation
MS-IBS-003 — Precast Stair Installation
MS-IBS-004 — Bathroom Pod Installation
MS-IBS-005 — Precast Joint Grouting and Connections
MS-FEF-001 — Curtain Wall Installation
MS-FEF-002 — Aluminium Composite Panel Cladding
MS-FEF-003 — Façade Stone Cladding
MS-FEF-004 — External Render and Protective Coating
MS-FEF-005 — Façade Water-Tightness Testing
MS-TNC-001 — LV Electrical Testing and Commissioning
MS-TNC-002 — ACMV Testing, Adjusting and Balancing
MS-TNC-003 — Fire Alarm Testing and Commissioning
MS-TNC-004 — Fire Pump and Sprinkler System Commissioning
MS-TNC-005 — Water Pipe Pressure Testing, Flushing and Disinfection
MS-SME-001 — Building Management System Installation and Integration
MS-SME-002 — CCTV System Installation and Commissioning
MS-SME-003 — Access Control System
MS-SME-004 — Structured Cabling and Data Network
MS-SME-005 — Solar Photovoltaic System
MS-HRB-001 — Self-Climbing Jumpform and Core Wall Construction
MS-HRB-002 — Post-Tensioned Concrete Slab
MS-HRB-003 — Tower Crane Erection, Climbing and Dismantling
MS-HRB-004 — Construction Hoist Installation, Operation and Dismantling
MS-HRB-005 — High-Level Concrete Pumping
MS-HRB-006 — Lift and Escalator Installation
MS-HRB-007 — Fire-Stopping of M&E Penetrations
MS-HRB-008 — Staircase and Lift Shaft Pressurisation System
MS-HRB-009 — High-Rise Booster Pump and Water Transfer System
MS-HRB-010 — Building Maintenance Unit and Façade Access System
MS-CRP-001 — Concrete Condition Survey, Defect Mapping and Diagnostic Testing
MS-CRP-002 — Temporary Propping and Load Relief for Concrete Repair
MS-CRP-003 — Controlled Concrete Breakout and Hydrodemolition
MS-CRP-004 — Corroded Reinforcement Cleaning, Passivation and Replacement
MS-CRP-005 — Hand-Applied Cementitious Patch Repair
MS-CRP-006 — Form-and-Pour Repair Using Microconcrete
MS-CRP-007 — Sprayed Concrete and Gunite Repair
MS-CRP-008 — Epoxy Injection of Structural Cracks
MS-CRP-009 — Polyurethane Resin Injection for Water-Leak Sealing
MS-CRP-010 — Routing and Sealing of Non-Structural Cracks
MS-CRP-011 — Honeycomb, Void and Cold-Joint Repair
MS-CRP-012 — Dry-Pack and Grouting Repair to Base Plates, Bearings and Pockets
MS-CRP-013 — Structural Strengthening Using CFRP
MS-CRP-014 — Bonded and Bolted Steel-Plate Strengthening
MS-CRP-015 — Concrete Jacketing and Structural Section Enlargement
MS-CRP-016 — Post-Installed Dowel and Chemical-Anchor Installation
MS-CRP-017 — Corrosion Inhibitor and Embedded Galvanic-Anode Treatment
MS-CRP-018 — Cathodic Protection System for Concrete Structures
MS-CRP-019 — Anti-Carbonation and Chemical-Resistant Protective Coating
MS-CRP-020 — Concrete Expansion-Joint Repair and Replacement
MS-CRP-021 — Fire-Damaged Concrete Assessment and Repair
MS-CRP-022 — Industrial Concrete-Floor and Joint-Arris Repair
MS-CRP-023 — Underwater and Splash-Zone Concrete Repair
MS-CRP-024 — Negative-Side Waterproofing and Crystalline Concrete Treatment
MS-SRS-001 — Contiguous Bored-Pile Retaining Wall
MS-SRS-002 — Secant Bored-Pile Retaining Wall
MS-SRS-003 — Sheet-Pile Retaining Wall
MS-SRS-004 — Soldier-Pile and Lagging Retaining Wall
MS-SRS-005 — Prestressed Ground Anchor and Tieback Installation
MS-SRS-006 — Retaining-Wall Capping Beam Construction
MS-SRS-007 — Jet-Grouted Cut-Off and Ground-Improvement Wall
MS-SRS-008 — Deep-Soil-Mixing Retaining and Cut-Off Wall
MS-SRS-009 — Retaining-Structure Instrumentation and Movement Monitoring
MS-SPG-001 — Prestressed-Concrete Spun-Pile Installation
MS-SPG-002 — Precast Reinforced-Concrete Pile Installation
MS-SPG-003 — Hydraulic Jack-In or Injection Pile Installation
MS-SPG-004 — Driven Steel H-Pile Installation
MS-SPG-005 — Driven Steel Pipe-Pile Installation
MS-SPG-006 — Continuous-Flight-Auger Pile Installation
MS-SPG-007 — Barrette Pile Construction
MS-SPG-008 — Static Pile Load Testing
MS-SPG-009 — Pile Integrity and Dynamic Load Testing
