METHOD STATEMENT PACKAGE — INDUSTRIAL BUILDING

Total method statements: 43
Total editable Microsoft Word files: 86 (43 English + 43 Bahasa Malaysia)

IMPORTANT
Every template must be reviewed and adapted by a competent project team against the contract, approved drawings, project specification, actual site conditions, approved materials, manufacturer instructions, applicable Malaysian legal requirements and the Consultant's submission procedure before use.

CONTENTS
MS-CST-001 — Site Clearing and Disposal
MS-CST-002 — Surveying and Setting Out
MS-CST-003 — Earth Excavation
MS-CST-004 — Filling and Compaction
MS-CST-006 — Reinforcement Installation
MS-CST-007 — Concrete Formwork
MS-CST-008 — Reinforced Concrete Placement
MS-CST-009 — Precast Concrete Installation
MS-CST-010 — Structural Steel Fabrication and Erection
MS-ARC-006 — Painting Works
MS-ARC-008 — Door and Ironmongery Installation
MS-ARC-010 — Roofing System Installation
MS-MEP-001 — Electrical Conduit and Trunking
MS-MEP-002 — Cable Pulling and Termination
MS-MEP-003 — Distribution Board Installation
MS-MEP-004 — Earthing and Lightning Protection
MS-MEP-005 — Domestic Water Pipework
MS-MEP-006 — Sanitary and Waste Pipework
MS-MEP-007 — Fire Sprinkler Pipework
MS-MEP-008 — Fire Alarm System
MS-MEP-009 — ACMV Ductwork Installation
MS-MEP-010 — ACMV Pipework and Insulation
MS-INF-001 — Road Subbase and Roadbase
MS-INF-002 — Asphalt Pavement
MS-INF-003 — Kerb and Channel
MS-INF-004 — Surface Drainage
MS-INF-005 — Sewer Pipeline
MS-INF-006 — Water Reticulation
MS-INF-007 — Street Lighting and External Cabling
MS-INF-008 — Soft Landscape Works
MS-SAF-001 — Mobilisation, Hoarding and Site Facilities
MS-SAF-002 — Scaffold Erection and Dismantling
MS-SAF-003 — Crane Lifting Operations
MS-SAF-004 — Confined Space Work
MS-SAF-005 — Hot Work
MS-SAF-006 — Temporary Dewatering
MS-SAF-007 — Controlled Demolition
MS-TNC-001 — LV Electrical Testing and Commissioning
MS-TNC-002 — ACMV Testing, Adjusting and Balancing
MS-TNC-003 — Fire Alarm Testing and Commissioning
MS-TNC-004 — Fire Pump and Sprinkler System Commissioning
MS-TNC-005 — Water Pipe Pressure Testing, Flushing and Disinfection
MS-SME-005 — Solar Photovoltaic System
