METHOD STATEMENT PACKAGE — RAILWAY

Total method statements: 59
Total editable Microsoft Word files: 118 (59 English + 59 Bahasa Malaysia)

IMPORTANT
Every template must be reviewed and adapted by a competent project team against the contract, approved drawings, project specification, actual site conditions, approved materials, manufacturer instructions, applicable Malaysian legal requirements and the Consultant's submission procedure before use.

CONTENTS
MS-CST-002 — Surveying and Setting Out
MS-CST-003 — Earth Excavation
MS-CST-004 — Filling and Compaction
MS-CST-006 — Reinforcement Installation
MS-CST-007 — Concrete Formwork
MS-CST-008 — Reinforced Concrete Placement
MS-MEP-001 — Electrical Conduit and Trunking
MS-MEP-002 — Cable Pulling and Termination
MS-MEP-003 — Distribution Board Installation
MS-MEP-004 — Earthing and Lightning Protection
MS-MEP-005 — Domestic Water Pipework
MS-MEP-006 — Sanitary and Waste Pipework
MS-MEP-007 — Fire Sprinkler Pipework
MS-MEP-008 — Fire Alarm System
MS-MEP-009 — ACMV Ductwork Installation
MS-MEP-010 — ACMV Pipework and Insulation
MS-INF-001 — Road Subbase and Roadbase
MS-INF-002 — Asphalt Pavement
MS-INF-003 — Kerb and Channel
MS-INF-004 — Surface Drainage
MS-INF-005 — Sewer Pipeline
MS-INF-006 — Water Reticulation
MS-INF-007 — Street Lighting and External Cabling
MS-INF-008 — Soft Landscape Works
MS-SAF-001 — Mobilisation, Hoarding and Site Facilities
MS-SAF-002 — Scaffold Erection and Dismantling
MS-SAF-003 — Crane Lifting Operations
MS-SAF-004 — Confined Space Work
MS-SAF-005 — Hot Work
MS-SAF-006 — Temporary Dewatering
MS-SAF-007 — Controlled Demolition
MS-BRI-001 — Bridge Pile Cap Construction
MS-BRI-002 — Bridge Pier and Pier Head
MS-BRI-003 — Precast Bridge Beam Erection
MS-BRI-004 — Bridge Deck Slab
MS-BRI-005 — Bridge Bearings and Expansion Joints
MS-TNC-001 — LV Electrical Testing and Commissioning
MS-TNC-002 — ACMV Testing, Adjusting and Balancing
MS-TNC-003 — Fire Alarm Testing and Commissioning
MS-TNC-004 — Fire Pump and Sprinkler System Commissioning
MS-TNC-005 — Water Pipe Pressure Testing, Flushing and Disinfection
MS-BRI-006 — Cofferdam and In-Water Foundation Works
MS-BRI-007 — Bridge Prestressing and Tendon Grouting
MS-BRI-008 — Cast-In-Situ Box Girder and Form Traveller
MS-BRI-009 — Segmental Erection Using Launching Girder
MS-BRI-010 — Bridge Parapet and Vehicle Barrier
MS-BRI-011 — Bridge Deck Waterproofing and Asphalt Surfacing
MS-BRI-012 — Bridge Drainage System
MS-BRI-013 — Bridge Load Testing and Structural Monitoring
MS-TPL-001 — Pipe-Jacking Installation
MS-TPL-002 — Slurry Microtunnelling Installation
MS-TPL-003 — Horizontal Directional Drilling
MS-TPL-004 — Horizontal Auger-Boring Pipe Crossing
MS-TPL-005 — Pneumatic Pipe-Ramming Installation
MS-TPL-006 — Trenchless Launch and Reception Shaft Construction
MS-TPL-007 — Trenchless-Pipeline Annulus Grouting
MS-TPL-008 — Pipe-Bursting Replacement of Existing Pipeline
MS-TPL-009 — Cured-in-Place Pipe Relining
MS-TPL-010 — Existing-Pipeline Sliplining
